UDK-06

UDK-06

Emergency lighting and evacuation route signs for the Drammen Tunnel.

Client: Caverion Norge AS

Period: 2022 - 2025

Delivery: Tunnel Guidance Lighting

Application: Railway – Tunnel Emergency Lighting

The challenge

Bane NOR is constructing a new double-track railway from Drammen to Kobbervikdalen. The new Drammen Tunnel forms part of the new double-track section south of Drammen and is almost 7 kilometres long. Caverion is responsible for the electrical works, including the emergency lighting system in the new tunnel. The main tunnel was to be equipped with emergency lighting and evacuation route signs in accordance with Bane NOR’s Technical Regulations (TRV). Proxll was selected to supply the complete system, consisting primarily of handrails with integrated LED lighting, photoluminescent evacuation signs, emergency exit marker lights and emergency lighting control units, as well as the associated engineering and design. The tunnel was scheduled to open for operation in August/September 2025.

The solution

Proxll had already entered into an agreement with Döllken Profiles GmbH for the production of handrails and LED strips. The contract with Caverion was signed in early 2022, while the engineering work and the majority of the equipment deliveries were largely completed in Q1 2024. In parallel, Proxll also supplied point heating systems for the project. The project was carried out during a challenging period, affected by the COVID-19 pandemic and the outbreak of the war in Ukraine. Close cooperation and continuous dialogue with Döllken and Caverion were therefore essential to the successful execution of the project.

The result

Proxll, in collaboration with Döllken Profiles, has developed a system that integrates multiple lighting functions into a single solution. This provides significant cost savings for both the contractor and the client, as all cabling can be integrated into the handrail. Although the tunnel is not yet in operation, Bane NOR is very satisfied with the evacuation and lighting system installed in both the main tunnel and the escape tunnels.

 

In June 2025, a delegation from NoBo, an EU-recognised body authorised to verify that railway infrastructure, rolling stock and systems comply with the EU’s Technical Specifications for Interoperability (TSI), carried out an inspection and identified zero non-conformities. The delegation also stated that the Drammen Tunnel was the best they had seen. This is a significant recognition of the quality of the work delivered by both Caverion and Proxll.

Proxll supplied a complete evacuation and emergency lighting system for the new Drammen Tunnel, part of Bane NOR’s double-track railway project between Drammen and Kobbervikdalen. The system integrates emergency lighting, photoluminescent signs and marker lights into a single handrail solution, providing significant cost savings. The solution received excellent results during the EU inspection and was described as the best they had seen.